Tech companies need more data centers . So why are nearly half of all planned projects delayed or canceled ?

Global hyperscale spending on AI infrastructure is projected at about $700 billion, yet the article says 30% to 50% of the 16 GW of U.S. data center capacity scheduled to come online faces severe delays or cancellation. Causes include lengthy permitting, a shortage of roughly 439,000 skilled construction workers, electrical equipment deficits, and grid interconnection queues that stretch four to seven years in markets like Northern Virginia, Phoenix and Dallas. Sandstone Group reports that nearly half of planned U.S. data centers are behind schedule. As an example, Oracle and OpenAI shelved plans to expand the Abilene, Texas campus developed by Crusoe Energy from 1.2 GW to 2.0 GW after prolonged negotiations over financing and utility timelines stalled. A typical AI data center can consume as much electricity as 100,000 households, and the largest campuses under construction will use 20 times that.

Summary written by Upside AI from the original article. Read the source for full details.

Original headline: Tech companies need more data centers . So why are nearly half of all planned projects delayed or canceled ?

Read the original on abc17news.com ↗

Keywords

data centersAI investmentNVDAelectricity

Open a keyword to see other news on the same topic.

Related tickers and likely impact

NVDA

▼ Likely negative

Nvidia

Relevance: low

MarketUS stocks
SectorInformation Technology
IndustrySemiconductors
Market cap$5.2T
Close on 10/19/2026217.09
Change that session+1.38%
NVDA price, forecasts and signals →

Impact is scored by AI from the headline and may be wrong. It is not investment advice.

Related news

  • Tech companies need more data centers . So why are nearly half of all planned projects delayed or canceled ?

    Spending on AI infrastructure is projected at about $700 billion through global hyperscale spending, yet building U.S. data centers is hitting bottlenecks in industrial supply chains and grid capacity rather than chip shortages. Industry research cited in the article finds that 30%–50% of the 16 GW of U.S. data center capacity scheduled to come online faces severe delays or cancellation. Causes include lengthy permitting, a shortage of roughly 439,000 skilled construction workers, electrical equipment deficits, and grid interconnection queues of four to seven years in Northern Virginia, Phoenix and Dallas. Oracle and OpenAI scrapped plans to expand the Crusoe Energy-developed campus in Abilene, Texas, from 1.2 GW to 2.0 GW after talks over financing and utility timelines stalled.

    marshfieldmail.com·• NVDAdata centersAI investmentNVDA
  • Data Center Buildout Now the Largest Financial Bet in U . S . History – Pagosa Daily Post News Events & Video for Pagosa Springs Colorado

    According to Stateline, U.S. data center investment for AI has surpassed all past booms in scale and is crowding out more job-creating sectors. A Columbia Business School report by Stijn Van Nieuwerburgh estimates $10 trillion in investment, with an economic impact of nearly 4% of GDP, almost twice that of railroad expansion in the late 1800s. Many states that granted tax exemptions earlier are now pulling back, as Nevada trimmed abatements and will require data centers to cover energy and water costs. Over three years, Texas ($638 billion), Virginia ($249 billion), Ohio ($169 billion) and Georgia ($160 billion) are projected to see the largest costs, according to Industrial Info Resources. Data center construction value has more than doubled to $85 billion a year while other construction fell 8%, and the profitability of AI remains unproven.

    pagosadailypost.com·▲ AMZN▲ GOOGL▲ META▲ MSFTdata centersAI investmentelectricity
  • GE Vernova vs. Caterpillar: Which Has More Exposure to the AI Power Build-Out?

    The article compares GE Vernova and Caterpillar in terms of their exposure to AI infrastructure spending. Analysts expect AI capital expenditures to reach $800 billion this year, and Goldman Sachs says hyperscaler investment could hit $1.7 trillion by 2027 and $2.1 trillion by 2029. GE Vernova has greater exposure to this trend, with strong demand for gas turbines and electrification equipment; its data center orders in electrification doubled to $5 billion in the first half of 2026, and its total backlog reached $176 billion. Caterpillar benefits from demand for backup power systems, with a $72 billion backlog, power-generation sales up 72% from last year, and gas turbine order backlogs stretching to 2030. Both stocks have been highly volatile: GE Vernova is up 596% and Caterpillar up 149% since the start of 2024, but they are 23% and 32% below their 52-week highs, respectively.

    Yahoo Finance·AI investmentdata centerselectricity
  • The next industrial revolution ?

    The article traces earlier industrial revolutions, when services' share of US and UK GDP rose to around 80% and 75% by 2016, and argues the fourth, driven by AI, resembles the first because it requires heavy material investment. AI consumes about 400 terawatt-hours a year, roughly 1.5% of world electricity, and the IEA projects this could more than double by 2030. Estimated data-centre infrastructure spending could reach $7 trillion, about 30% of US GDP, while Alphabet, Amazon, Microsoft and Meta plan $725 billion in capital expenditure, up 77% from a year ago. The author argues this capital-heavy growth is likely to be inflationary and push bond yields higher, which could threaten the viability of public debt in overindebted countries.

    cyprus-mail.com·artificial intelligenceAI investmentdata centers
  • Microsoft Signs 1,100 MW Power Deal With NiSource Until 2048 as AI Spending Outruns the Grid

    NiSource (NI) announced a 20-year energy agreement with Microsoft starting in 2028, adding about 1,100 MW to its generation pool for an Indiana data-center campus, with Microsoft paying for all the generation and transmission needed to serve the site. That capacity is roughly what Microsoft brings online in a full quarter, while its cash capex grew from $23.9 billion in fiscal 2022 to $116 billion in fiscal 2026, almost five times as much. Much of that spending goes to short-lived CPUs and GPUs that earn nothing until power is available, and management expects the broader capex measure to grow again in fiscal 2027, starting with more than $50 billion in the September quarter. NiSource signed Alphabet and expanded its Amazon agreement in April, so three hyperscalers now have power deals with the same Indiana utility.

    Yahoo Finance·▲ MSFTMSFTdata centerselectricity
  • Tech companies need more data centers . So why are nearly half of all planned projects delayed or canceled ?kono1011.com·▼ NVDANVDAdata centersartificial intelligence

Related markets

US stocks →

Latest news

  • Amazon blocks agentic AI shopping. But Walmart is betting big that it's worth saying yes.

    A Bank of America note led by Christopher Nardone, published Monday, argues Walmart stands to benefit if shoppers hand purchases to AI agents, citing its integration with multiple AI ecosystems, its own shopping assistant “Sparky” and partnerships including Meta's Muse. Walmart, Best Buy (BBY) and Ulta (ULTA) are among Muse's key partners, while some other retailers have blocked it. Amazon has blocked Muse from making purchases on its site and bars automated shopping tools, though it may not be losing much in sales since most people use AI mainly for research. Walmart's management, however, cannot say how popular shopping agents will become, and it is unclear how advertising, a growing business for Walmart, would be affected if screenless computers handle checkout.

    Yahoo Finance·• AMZNAMZNWalmartretail
  • Stocks are driving consumption 'like never before' — and that exposes a big risk

    In a note published Monday, Doug Peta, chief US investment strategist at BCA Research, argues the stock market is influencing the economy like never before. US household net worth reached over eight times disposable income at midyear, an all-time high, and the value of household equity holdings is nearly three times annual after-tax income. Peta estimates that a 10% gain in the S&P 500 over a year boosts household spending capacity as much as a 28% raise, making consumption more sensitive to equity moves. That sensitivity cuts both ways, as a future bear market could amplify spending pullbacks because households would feel vulnerable rather than wealthy.

    Yahoo Finance·• QQQ• SPYS&P 500USconsumer spending
  • H.I.G. WhiteHorse Provides Financing to Be-Cloud and QualityHosting

    H.I.G. WhiteHorse, the credit affiliate of H.I.G. Capital, has arranged a debt package to finance QualityHosting's acquisition of Be-Cloud, with QualityHosting being a portfolio company of PSG Equity. The package also provides additional capital for the combined company's future growth and M&A strategy. Be-Cloud, founded in 2012 and headquartered in France, is a leading European Microsoft Cloud Solution Provider with more than 37,500 active end customers and over 1,000 reseller and MSP partners. QualityHosting, a German Microsoft CSP, serves more than 30,000 end customers and has about 1,000 reseller partners.

    Yahoo Finance·creditmergers and acquisitionsFrance
  • Residential electricity prices may be set by peak and off-peak hours

    Vietnam's Minister of Industry and Trade, Lê Mạnh Hùng, submitted to the National Assembly on the afternoon of October 20 a draft amendment to the Electricity Law. It would allow retail electricity to be priced by peak, off-peak and normal hours where technical conditions allow, with a roadmap for applying this to residential customers. The draft also sets out a plan to eliminate cross-subsidies between customer groups and proposes incentive pricing for renewable energy, new energy and storage systems. Nguyễn Thanh Hải, chair of the National Assembly's Committee for Science, Technology and Environment, asked that the scope and roadmap for removing cross-subsidies and electricity bill support be clarified, kept separate from direct aid to poor households, and that investment risks not be shifted to the State or the public. The committee also warned that the wording requiring full recovery of costs and reasonable profit could be read as the State guaranteeing investors' financial results.

    CafeF·electricityVietnamregulation
  • HoSE officially announces roadmap for transferring nearly 300 HNX-listed stocks to trading on HoSE

    As of mid-October 2026, HNX had 299 listed stock codes with total market capitalisation of about 450,000 billion VND. On 20/10, HoSE announced the roadmap for reorganising trading of listed stocks under Circular 139/2025/TT-BTC, dated 30/12/2025, from the Ministry of Finance. The last trading day for all HNX-listed stocks is 23/12/2026, and the stocks being transferred will be suspended on 24 and 25/12/2026. From 28/12/2026, all listed stocks will trade on HoSE, and listed companies, market members and investors are urged to prepare in advance.

    CafeF·▲ VNINDEXVNINDEXexchangeslisting
  • South Korean IPO plunge deepens AI market jitters as brent tops $111

    South Korean data centre company Elice (0158S0) closed at 60,500 won ($45.57) on its debut, down over 30% from its 90,500 won offer price, despite a retail offering oversubscribed more than 400 times. The IPO raised $151 million at a valuation of roughly $755 million, according to Bloomberg. The debut came as the KOSPI dropped almost 4% to 5,552, with Samsung Electronics and SK Hynix also falling, and CoreWeave (CRWV) slipped another 3% in U.S. pre-market trading. Investors are questioning the borrowing costs, debt levels and returns of AI infrastructure spending, while Brent crude topped $111 a barrel, its highest since May, amid Middle East supply and shipping concerns.

    CoinDesk·▼ NVDA▼ QQQ▼ SPYIPOSouth Koreadata centers

All news →

Get the briefing on Telegram or Zalo

Join the Upside Telegram channel or Zalo group for the Vietnam stocks and gold briefing at 8:00 and 19:00 (Vietnam time) on trading days, plus a weekly wrap on Saturday morning.